Tenders
Specific Procurement Notice - Invitation for Prequalification for Construction of Highway E80,
Section Dimitrovgrad Bypass-Border Crossing, LOT 3: Tunnels Przojna Padina and Progon
published on Wednesday, 11th August 2010.
expires Wednesday, 29th September 2010.
|
Electronic version of standard forms which are part of prequalification documents can be downloaded from World Bank website |
General Procurement Notice (EIB)
published on Wednesday, 30th June 2010.
General Procurement Notice (EBRD)
published on Tuesday, 8th June 2010.
Works Contract Forecast
published on Tuesday, 11th August 2009.
Construction of Corridor X, Highway E-75 Niš – FYROM border
Section: Levosoje - Donji Neradovac, South of Serbia
pdf file_
Published in local newspapers:
- Politika
- Blic
- Večernje novosti,
Published in Greek newspapers:
- Naftemporiki
- Adesmeytos Typos
- Express Daily Financial
General Procurement Notice (WB)
published on Wednesday, 1st July 2009.
General Procurement Notice (WB)
The World Bank financed project will include the following components:
Part A. M-1 Road (E75) Corridor Xd.
Part B. M 1-12 Road (E80) Nis Dimitrovgrad Corridor Xc.
Part C. Road Safety.
Part D. Implementation Assistance and Institutional Support.
pdf file_
published on Friday, 30th July 2010.AlpineBau GmbH offered the lowest price for construction of Corridor X, Highway E80, section Pirot (East) - Dimitrovgrad

On Friday 30th July 2010 in the building of the Government a public opening of bids was held for awarding the contract for the construction of the highway E80, Section Pirot (East) - Dimitrovgrad.
Lowest price for the construction of the highway E 80, Section Pirot (East) - Dimitrovgrad, with all the discounts, offered the Austrian company AlpineBau GmbH, followed by the Slovenian ‘’Primorje ‘’d.d. and Serbian consortium comprising GP ‘’Planum’’, ‘’Putevi Uzice’’ and ‘’Preduzece za puteve Beograd’’ as third.
read more >>
published on Friday, 16th July 2010.Specific Procurement Notice for Construction of Highway E80, Section Pirot (East) – Dimitrovgrad, L=14.3 km
Deadline for the submission of bids is extended to July 30, 2010 by 12:00 hours, local time (GMT+1)
read more >>
published on Friday, 2nd July 2010.Clarification meeting for Construction of Highway E75, Nis – FYROM border, Section: Srpska Kuca - Donji Neradovac
Clarification meeting and guided site inspection with K10 representatives, prospective tenderers, Designer and representatives of Vranje municipality was held in Vranje on July 1, 2010.